Retail Recent Projects

25 Berkeley Square

  • Contract Value £1.4m
  • Client St George Central London Limited
  • Contract Period 11 Weeks
Berkeley Sq

The project for St George Central London Limited involved the transformation of the existing ground floor offices at 25 Berkeley Square into St George’s primary London property marketing suite. The works included the fast-track construction, reconfiguration, refurbishment, fit out and decoration of a mixture of offices, meeting rooms, new reception, bar, WC’s and a new staff kitchen.

Calvin Klein

  • Contract Value Confidential
  • Client Manchester Allied London
  • Contract Period N/A
Calvin Klein

The new Calvin Klein store project was carried out as part of a larger development project for Allied London and included the construction of a new shell & core, a new shop front and the fit-out of a store on The Avenue at Spinningfields in Manchester.

28 – 29 Savile Row

  • Contract Value £4.8m
  • Client Pavilion Property Trustees Limited London Limited
  • Contract Period 34 Weeks
Feature image

The main project consists of the refurbishment of the basement and floors 1 to 6 of 28-29 Savile Row and an extension to and refurbishment of the adjoined 15, Old Burlington Street. The works include the demolition of structural partition walls; removal and replacement of the façade and removal and replacement of ground floor retail shop front windows and doors.

Spens House

  • Contract Value £2.4m
  • Client London WC1 Serviced Apartment Company
  • Contract Period 34 Weeks
Feature image

Conversion of existing nurses accommodation into 32 nr 2-bed apartments to be rented as “apart-hotel” rooms. Works on this confined site included complete strip out & reconfiguration of the existing layout; installation of new M&E systems; extension of the 4th floor to create penthouse apartments.

Cardiff Bay Retail Park Unit G

  • Contract Value £400k
  • Client Atisreal Ltd
  • Contract Period 8 Weeks
Feature image

The project involved the reconfiguration of two adjacent retail units to form a single one. Works included internal demolition and structural alterations; refurbishment of the existing external cladding; creation of a new single front entrance with new automated doors; remedial works to the roller shutter doors to the rear; new ventilation systems; all associated M&E works and interior decorations.